[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112451":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1112451,787,1,"单选题","管道试压后的工序有（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","管段预制",false,{"key":16,"text":17,"correct":14},"B","管道安装",{"key":19,"text":20,"correct":21},"C","防腐绝热",true,{"key":23,"text":24,"correct":14},"D","管口焊接","2020版教材P76 1.工业管道工程的一般施工程序：施工准备—配合土建预留、预埋、测量—管道、支架预制—附件、法兰加工、检验—管段预制—管道安装—管道系统检验—管道系统试验—防腐绝热—系统清洗-资料汇总、绘制竣工图—竣工验收。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]