[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112445":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1112445,787,1,"单选题","管道系统压力试验前，管道上的膨胀节应（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","隔离",false,{"key":16,"text":17,"correct":14},"B","拆除",{"key":19,"text":20,"correct":21},"C","设置临时约束装置",true,{"key":23,"text":24,"correct":14},"D","处于自然状态","2020版教材P82 （6）试验结束后及时拆除盲板、膨胀节临时约束装置。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]