[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112391":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1112391,787,1,"单选题","无负荷联动试运转规程由（ ）负责编制。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设单位",false,{"key":16,"text":17,"correct":18},"B","施工单位",true,{"key":20,"text":21,"correct":14},"C","设计单位",{"key":23,"text":24,"correct":14},"D","监理单位","2020版教材P54 本题考查的是机械设备安装的一般程序和一般要求。无负荷单体和联动试运转规程由施工单位负责编制，并负责试运转的组织、指挥和操作，建设单位及相关方人员参加。负荷单体和联动试运转规程由建设单位负责编制，并负责试运转的组织、指挥和操作，施工单位及相关方可依据建设单位的委托派人参加。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]