[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112389":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1112389,787,1,"单选题","设备单体试运转的顺序是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","先电动，后手动；先点动，后连续；先低速，后中、高速",false,{"key":16,"text":17,"correct":14},"B","先手动，后电动；先连续，后点动；先低速，后中、高速",{"key":19,"text":20,"correct":21},"C","先手动，后电动；先点动，后连续；先低速，后中、高速",true,{"key":23,"text":24,"correct":14},"D","先手动，后电动；先点动，后连续；先中、高速，后低速","2020版教材P54 本题考查的是机械设备安装的一般程序和一般要求。设备单体试运转的顺序是：先手动，后电动；先点动，后连续；先低速，后中、高速。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]