[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112388":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1112388,787,1,"单选题","在安装现场，过盈配合件的装配方法主要采用（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","压入装配法",false,{"key":16,"text":17,"correct":14},"B","低温冷装配法",{"key":19,"text":20,"correct":14},"C","焊接固定法",{"key":22,"text":23,"correct":24},"D","加热装配法",true,"2020版教材P54 本题考查的是机械设备安装的一般程序和一般要求。过盈配合件的装配方法，一般采用压人装配、低温冷装配和加热装配法，而在安装现场，主要采用加热装配法。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]