[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112387":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1112387,787,1,"单选题","一次灌浆是设备粗找正后，对（ ）进行的灌浆。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","设备底座",false,{"key":16,"text":17,"correct":14},"B","设备基础间",{"key":19,"text":20,"correct":21},"C","地脚螺栓预留孔",true,{"key":23,"text":24,"correct":14},"D","设备底座和基础间","2020版教材P53 本题考查的是机械设备安装的一般程序和一般要求。设备灌浆分为一次灌浆和二次灌浆。一次灌浆是设备粗找正后，对地脚螺栓预留孔进行的灌浆。二次灌浆是设备精找正、±也脚螺栓紧固、检测项目合格后对设备底座和基础间进行的灌浆。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]