[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112357":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1112357,787,1,"单选题","有关管线工程的测量，正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","管线中心定位就是将控制点位置测设到地面上去",false,{"key":16,"text":17,"correct":14},"B","管线敷设临时水准点必须选在旧建筑物墙角、台阶等处",{"key":19,"text":20,"correct":21},"C","临时标桩可作为水准点",true,{"key":23,"text":24,"correct":14},"D","地下管线工程测量必须在回填后，测量出起、止点，窨井坐标和管顶标高","2020版教材P24 本题考查的是机电工程中常见的工程测量。选项A，管线中心定位是将主点位置测设到地面上去；选项B，错在“必须”；选项D，是在回填前。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]