[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112330":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1112330,787,1,"单选题","长距离输电线路钢塔架控制桩测量是根据（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","相邻桩",false,{"key":16,"text":17,"correct":18},"B","中心桩",true,{"key":20,"text":21,"correct":14},"C","首尾桩",{"key":23,"text":24,"correct":14},"D","折点处桩","2020版教材P24 中心桩测定后，一般采用十字线法和平行基线法进行控制，控制桩应根据中心桩测定，其允许偏差应符合规定。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]