[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112323":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1112323,787,1,"单选题","为了便于管线施工时引测高程，施工前应（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设临时的基准点",true,{"key":16,"text":17,"correct":18},"B","予组装管线",false,{"key":20,"text":21,"correct":18},"C","以实测管线起点标高为基准点",{"key":23,"text":24,"correct":18},"D","以实测的管线终点标高为基准点","2020版教材P24 2）管线高程控制的测量方法：为了便于管线施工时引测高程及管线纵、横断面测量，应设管线敷设临时水准点。其定位允许偏差应符合规定。只有A符合题意",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]