[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112322":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1112322,787,1,"单选题","在设备基础测量工作步骤中，设备基础放线的后一步工作是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","熟悉基础设计与开挖工艺",false,{"key":16,"text":17,"correct":14},"B","设备基础位置的确认",{"key":19,"text":20,"correct":14},"C","设备基础标高测量",{"key":22,"text":23,"correct":24},"D","标高基准点的确认",true,"2020版教材P23 设备基础的测量工作大体包括以下步骤：设备基础位置的确认，设备基础放线，标高基准点的确认，设备基础标高测量",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]