[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112193":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1112193,787,1,"单选题","合同管理文件中不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","材料采购总计划表",false,{"key":16,"text":17,"correct":14},"B","工程分包合同",{"key":19,"text":20,"correct":14},"C","劳务分包合同",{"key":22,"text":23,"correct":24},"D","设计变更",true,"本题考查的是二级建造师（机电工程）施工管理签章文件目录。合同管理文件包括：分包单位资质报审表；工程分包合同；劳务分包合同；材料采购总计划表；工程设备采购总计划表；工程设备、关键材料招标书和中标书；合同变更和索赔申请报告。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]