[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112179":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1112179,787,1,"单选题","建筑安装工程进行质量验收评定的工作程序是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","检验批验收→分部（子分部）工程验收→分项工程验收→单位（子单位）工程验收",false,{"key":16,"text":17,"correct":14},"B","检验批验收→单位（子单位）工程验收→分部（子分部）工程验收→分项工程验收",{"key":19,"text":20,"correct":14},"C","检验批验收→分项工程验收→单位（子单位）工程验收→分部（子分部）工程验收",{"key":22,"text":23,"correct":24},"D","检验批验收→分项工程验收→分部（子分部）工程验收→单位（子单位）工程验收",true,"本题考查的是建筑安装工程施工质量验收的项目划分和验收程序。建筑安装工程进行质量验收评定的工作程序是：检验批验收→分项工程验收→分部（子分部）工程验收→单位（子单位）工程验收。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]