[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112170":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1112170,787,1,"单选题","经返修或加固处理的分项、分部工程，虽然改变外形尺寸但仍能满足安全使用要求，可按（ ）和协商文件进行验收。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","设计图纸",false,{"key":16,"text":17,"correct":14},"B","设计变更",{"key":19,"text":20,"correct":21},"C","技术方案",true,{"key":23,"text":24,"correct":14},"D","合同文件","本题考查的是工业安装工程施工质量验收的组织与合格规定。经返修或加固处理的分项分部工程，虽然改变外形尺寸但仍能满足安全使用要求，可按技术方案和协商文件进行验收。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]