[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112168":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1112168,787,1,"单选题","工业安装分部工程验收的组织者是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","监理工程师",false,{"key":16,"text":17,"correct":18},"B","建设单位质量技术负责人",true,{"key":20,"text":21,"correct":14},"C","施工单位项目负责人",{"key":23,"text":24,"correct":14},"D","建设单位项目负责人","分部工程应在各分项工程验收合格的基础上，由施工单位（总承包单位）向建设单位（监理单位）提出报验申请，由建设单位质量技术负责人（总监理工程师）组织监理、设计、施工等有关单位质量技术负责人进行验收，并应填写验收记录。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]