[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112167":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1112167,787,1,"单选题","下列工业安装工程验收顺序正确的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","分项工程、单位工程、分部工程",false,{"key":16,"text":17,"correct":14},"B","分部工程、分项工程、单位工程",{"key":19,"text":20,"correct":14},"C","单位工程、分部工程、分项工程",{"key":22,"text":23,"correct":24},"D","分项工程、分部工程、单位工程",true,"工业安装工程施工质量验收应按分项工程、分部工程、单位工程依次进行。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]