[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112151":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1112151,787,1,"单选题","承包单位如果仅申请施工临时用电，那么施工临时用电结束或施工用电转入建设项目电力设施供电，则总承包单位应及时向供电部门办理（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","终止用电手续",true,{"key":16,"text":17,"correct":18},"B","新装用电手续",false,{"key":20,"text":21,"correct":18},"C","临时用电手续",{"key":23,"text":24,"correct":18},"D","变更用电手续","本题考查的是建设用电的规定。承包单位如果仅申请施工临时用电，那么，施工临时用电结束或施工用电转入建设项目电力设施供电，则总承包单位应及时向供电部门办理终止用电手续。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]