[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112137":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1112137,787,1,"单选题","封存的计量器具重新启用时，必须（ ），方可使用。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","确认其有合格证后",false,{"key":16,"text":17,"correct":18},"B","经检定合格后",true,{"key":20,"text":21,"correct":14},"C","经主管领导同意后",{"key":23,"text":24,"correct":14},"D","确认封存前是合格的","本题考查的是施工现场计量器具的管理程序。封存的计量器具重新启用时，必须经检定合格后，方可使用。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]