[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112123":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1112123,787,1,"单选题","机电工程项目试运行的最终阶段是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","单机试运行",false,{"key":16,"text":17,"correct":14},"B","联动试运行",{"key":19,"text":20,"correct":14},"C","空负荷试运行",{"key":22,"text":23,"correct":24},"D","负荷试运行",true,"本题考查的是试运行条件。负荷试运行是试运行的最终阶段，自装置接受原料开始至生产出合格产品、生产考核结束为止。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]