[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112121":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1112121,787,1,"单选题","试运行方案由项目总工程师组织编制后，审定人是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目部经理",false,{"key":16,"text":17,"correct":18},"B","企业总工程师",true,{"key":20,"text":21,"correct":14},"C","建设单位负责人",{"key":23,"text":24,"correct":14},"D","总监理工程师","本题考查的是试运行要求。试运行方案由施工项目总工程师组织编制，经施工企业总工程师审定，报建设单位或监理单位批准后实施。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]