[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112116":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1112116,787,1,"单选题","不属于应及时进行竣工验收的机电工程项目是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","达到环境保护要求，尚未取得环境保护验收登记卡",true,{"key":16,"text":17,"correct":18},"B","附属工程尚未建成，但不影响生产",false,{"key":20,"text":21,"correct":18},"C","形成部分生产能力，近期不能按设计规模续建",{"key":23,"text":24,"correct":18},"D","已投产，但一时达不到设计产能","本题考查的是竣工验收工作程序和要求。及时办理竣工验收的项目：（1）有的建设项目基本符合竣工验收标准，只是零星土建工程和少数非主要设备未按设计规定内容全部建成，但不影响正常生产的；（2）有的项目投产初期一时不能达到设计能力所规定的产量的；（3）有些建设项目或单项工程已形成部分生产能力或实际上生产方面已经使用。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]