[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112106":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1112106,787,1,"单选题","根据工程概况和招标文件，结合企业技术装备水平和建筑市场进行成本预测属于（）成本控制的内容。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","投标阶段",true,{"key":16,"text":17,"correct":18},"B","施工准备阶段",false,{"key":20,"text":21,"correct":18},"C","施工阶段",{"key":23,"text":24,"correct":18},"D","竣工验收阶段","本题考查的是施工成本计划的实施。根据工程概况和招标文件，结合企业技术装备水平和建筑市场进行成本预测，根据竞争对手的情况提出投标决策意见。以投标报价为依据确定项目的成本目标，并下达给现场施工项目部。是投标阶段的成本控制的内容。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]