[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112104":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1112104,787,1,"单选题","机电工程项目在施工阶段成本控制的内容是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","加强施工任务单和限额领料单的管理",true,{"key":16,"text":17,"correct":18},"B","结合企业技术水平和建筑市场进行成本预测",false,{"key":20,"text":21,"correct":18},"C","制订科学先进和经济合理的施工方案",{"key":23,"text":24,"correct":18},"D","编制施工费用预算并进行明细分解","本题考查的是施工成本计划的实施。选项B属于投标阶段的控制；选项C、选项D属于施工准备阶段的控制。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]