[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112103":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1112103,787,1,"单选题","在编制项目施工成本计划时，不采用的方法是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","按项目工序成本编制成本计划的方法",true,{"key":16,"text":17,"correct":18},"B","按成本构成编制成本计划的方法",false,{"key":20,"text":21,"correct":18},"C","按工程实施阶段编制成本计划的方法",{"key":23,"text":24,"correct":18},"D","按项目结构编制成本计划的方法","本题考查的是施工成本控制的依据。成本计划编制方法： （1）按成本构成编制成本计划的方法。 （2）按项目结构编制成本计划的方法。 （3）按工程实施阶段编制成本计划的方法。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]