[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112101":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1112101,787,1,"单选题","列选项属于降低项目施工成本的经济措施的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","选用适当的合同结构模式",false,{"key":16,"text":17,"correct":14},"B","建立分工明确、责任到人的成本管理责任体系",{"key":19,"text":20,"correct":21},"C","控制间接费及其他直接费",true,{"key":23,"text":24,"correct":14},"D","对不同施工方案进行技术经济比较","本题考查的是降低施工成本的措施。选项 A 属于合同措施；选项 B 属于组织措施；选项 D 属于技术措施。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]