[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112100":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1112100,787,1,"单选题","下列协调内容中，属于与土建单位沟通协调的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程综合进度的协商与协调",false,{"key":16,"text":17,"correct":14},"B","随时沟通现场施工中的进度.质量.安全",{"key":19,"text":20,"correct":14},"C","材料代用的协商与沟通",{"key":22,"text":23,"correct":24},"D","交叉施工的协商与配合",true,"本题考查的是沟通协调。与土建单位的沟通与协调包括：综合施工进度的平衡及进度的衔接与配合；交叉施工的协商与配合；吊装及运输机具、周转材料等相互就近使用与协调；重要设备基础、预埋件、吊装预留孔洞的相互配合与协调；土建施工质量问题的反馈及处理意见的协商；土建工程交付安装时的验收与交接。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]