[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112098":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1112098,787,1,"单选题","在地下设施、文物和资源保护方面，做法错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工前应调查清楚地下各种设施",false,{"key":16,"text":17,"correct":14},"B","施工过程中一旦发现文物，立即停止施工",{"key":19,"text":20,"correct":14},"C","按有关规定妥善处理后，可继续施工",{"key":22,"text":23,"correct":24},"D","施工过程中应做好保护计划",true,"本题考查的是现场绿色施工措施。选项D错误，施工前应调查清楚地下各种设施，做好保护计划，保证施工场地周边的各类管道 、管线、建筑物、构筑物的安全。地下各种设施的保护计划应施工前做好，并不是在施工过程中做。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]