[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112083":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1112083,787,1,"单选题","下列关于机电工程进度计划编制要点的说法中，错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","确定机电工程的施工顺序",false,{"key":16,"text":17,"correct":14},"B","突出主要分部分项工程",{"key":19,"text":20,"correct":21},"C","满足先地上后地下的施工顺序",true,{"key":23,"text":24,"correct":14},"D","满足先干线后支线的施工顺序","要满足先地下后地上、先干线后支线的施工顺序要求。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]