[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112082":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1112082,787,1,"单选题","施工进度计划调整的对象是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","主要工作",false,{"key":16,"text":17,"correct":18},"B","关键工作",true,{"key":20,"text":21,"correct":14},"C","非关键工作",{"key":23,"text":24,"correct":14},"D","次要工作","本题考查的是施工进度偏差分析与调整。施工进度计划调整的对象必须是关键工作，并且该工作有压缩的潜力，同时与其他可压缩对象相比赶工费是最低的。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]