[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112081":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1112081,787,1,"单选题","下列关于进度计划的相关表述中，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","横道图不能明确反映关键工作和关键线路",false,{"key":16,"text":17,"correct":18},"B","横道图能反映出工作所具有的机动时间",true,{"key":20,"text":21,"correct":14},"C","网络图能够明确表达各项工作之间的逻辑关系",{"key":23,"text":24,"correct":14},"D","横道图不利于施工进度的动态控制","本题考查的是单位工程施工进度计划实施。选项B的正确描述为“横道图不能反映出工作所具有的机动时间”。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]