[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112080":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1112080,787,1,"单选题","下列因素中，会影响施工图纸提供不及时的因素是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","拖欠工程进度款",false,{"key":16,"text":17,"correct":18},"B","规范标准的修订",true,{"key":20,"text":21,"correct":14},"C","现场的管控能力",{"key":23,"text":24,"correct":14},"D","新施工技术交底","本题考查的是施工进度的监测与调整。 施工图纸提供不及时，建设单位对工程提出了新的要求、规范标准的修订、设计单位对设计图纸的变更或施工单位要求施工修改，都会影响施工进度。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]