[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112079":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1112079,787,1,"单选题","采用横道图的方式所表达的进度计划，可以通过（ ）来进行偏差分析。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","计划线长度与实际线长度比较法",true,{"key":16,"text":17,"correct":18},"B","列表比较法",false,{"key":20,"text":21,"correct":18},"C","S曲线比较法",{"key":23,"text":24,"correct":18},"D","前锋线比较法","本题考查的是施工进度偏差分析与调整。选项B、选项C和选项D均是对网络图形式表达的计划进行偏差分析的方法。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]