[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112078":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1112078,787,1,"单选题","下图是某设备安装施工进度计划，该机电工程进度计划的总工期是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","85天",false,{"key":16,"text":17,"correct":14},"B","110天",{"key":19,"text":20,"correct":14},"C","160天",{"key":22,"text":23,"correct":24},"D","180天",true,"本题考查的是机电工程施工进度计划表示方法。网络计划关键工作如下图所示： 总工期为60+75+25+20=180天。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]