[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112075":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1112075,787,1,"单选题","下列选项中，不属于施工技术交底依据的是（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目质量策划",false,{"key":16,"text":17,"correct":14},"B","施工组织设计",{"key":19,"text":20,"correct":21},"C","资源供应情况",true,{"key":23,"text":24,"correct":14},"D","施工图纸","资源供应情况属于施工施工组织设计编制依据，不属于施工交底的依据",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]