[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112074":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1112074,787,1,"单选题","下列工程变更中，不属于重大设计变更的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工艺方案变化",false,{"key":16,"text":17,"correct":14},"B","增加单项工程",{"key":19,"text":20,"correct":14},"C","扩大设计规模",{"key":22,"text":23,"correct":24},"D","满足用户需求",true,"本题考查的是设计变更程序。重大设计变更是指变更对项目实施总工期和里程碑产生影响，或改变工程质量标准、整体设计功能，或增加的费用超出批准的基础设计概算，或增加原批准概算中没有列入的单项工程，或工艺方案变化、扩大设计规模、增加主要工艺设备等改变基础设计范围等原因提出的设计变更。重大设计变更应按照有关规定办理审批手续。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]