[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112067":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1112067,787,1,"单选题","施工现场材料管理的全面领导责任人是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目经理",true,{"key":16,"text":17,"correct":18},"B","材料员",false,{"key":20,"text":21,"correct":18},"C","项目部主管材料员",{"key":23,"text":24,"correct":18},"D","项目工长","本题考查的是工程材料管理的要求。施工项目经理是现场材料管理全面领导责任者，施工项目部主管材料人员是施工现场材料管理直接责任人。材料员在主管材料人员业务指导下，协助班组长组织和监督本班组合理领、用、退料。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]