[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112056":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1112056,787,1,"单选题","室内隐蔽或埋地的排水管在隐蔽前，必须做（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","压力试验",false,{"key":16,"text":17,"correct":14},"B","通球试验",{"key":19,"text":20,"correct":21},"C","灌水试验",true,{"key":23,"text":24,"correct":14},"D","泄漏试验","本题考查的是建筑管道工程施工技术要点。室内隐蔽或埋地的排水管道在隐蔽前必须做灌水试验，灌水高度不应低于底层卫生器具的上边缘或底层地面高度。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]