[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112040":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1112040,787,1,"单选题","关于曳引式电梯安装的施工程序，顺序正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设备进场验收→开箱点件→安装样板架.放线→轨道安装",true,{"key":16,"text":17,"correct":18},"B","开箱点件→安装样板架.放线→轨道安装→曳引绳安装",false,{"key":20,"text":21,"correct":18},"C","轨道安装→轿厢组装→缓冲器和对重装置安装→曳引机和机房其他设备安装",{"key":23,"text":24,"correct":18},"D","曳引绳安装→缓冲器和对重装置安装→厅门安装→电气装置安装","本题考查的是电梯工程施工程序。电力驱动的曳引式或强制式电梯施工程序：清理底坑、搭脚手架、井道测量、验收交接→设备进场验收→开箱点件→安装样板架、放线→轨道安装→轿厢组装→曳引机和机房其他设备安装→缓冲器和对重装置安装→曳引绳安装→厅门安装→电气装置安装→调试验收→试运转。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]