[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112027":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1112027,787,1,"单选题","混合储存装置的安装属于（ ）的子分部工程的分项工程。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","气体灭火系统",false,{"key":16,"text":17,"correct":14},"B","固定消防炮灭火系统",{"key":19,"text":20,"correct":21},"C","泡沫灭火系统",true,{"key":23,"text":24,"correct":14},"D","干粉灭火系统","本题考查的是消防工程的划分。泡沫灭火系统的分项工程包括：管道安装，阀门安装，泡沫发生器的安裝，混合储存装置的安装，系统调试，系统验收等分项工程。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]