[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112026":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1112026,787,1,"单选题","按照国家工程建设消防技术标准的规定，建设单位在验收后应当报消防部门备案的工程是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建筑总面积10000m2的广播电视楼",false,{"key":16,"text":17,"correct":18},"B","建筑总面积800m2的中学教学楼",true,{"key":20,"text":21,"correct":14},"C","建筑总面积550m2的卡拉OK厅",{"key":23,"text":24,"correct":14},"D","建筑总面积20000m2的客运车站候车室","人员密集场所消防验收规定",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]