[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112017":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1112017,787,1,"单选题","下列关于建筑智能化系统，线缆施工的说法错误的是（）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","线缆敷设前，应做电气导通检查",false,{"key":16,"text":17,"correct":14},"B","线路敷设完毕后，应做电气导通检查",{"key":19,"text":20,"correct":21},"C","用兆欧表测量线缆绝缘电阻，电阻值不应小于1MΩ",true,{"key":23,"text":24,"correct":14},"D","信号线缆与电力电缆交叉敷设时，宜成直角","1）线缆敷设前，应做电缆外观及电气导通检查。用兆欧表测量绝缘电阻，其电阻值不应小于0.5MΩ。 2）信号线缆和电力电缆平行或交叉敷设时，其间距不得小于0.3m；信号线缆与电力电缆交叉敷设时，宜成直角。 8）线路敷设完毕，应进行校验及标号，并再次做外观及导通检查。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]