[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112013":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1112013,787,1,"单选题","风管、部件及空调设备绝热工程施工应在（ ）进行。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","空调水系统试验后",false,{"key":16,"text":17,"correct":14},"B","设备单机调试后",{"key":19,"text":20,"correct":21},"C","风管系统严密性试验后",true,{"key":23,"text":24,"correct":14},"D","风管系统严密性试验前","本题考查的是通风与空调防腐绝热的技术要求。风管、部件及空调设备绝热工程施工应在风管系统严密性试验合格后进行。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]