[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112010":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1112010,787,1,"单选题","换热器及密闭容器在连接管道前，应进行（ ）试验。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","水压",true,{"key":16,"text":17,"correct":18},"B","满水",false,{"key":20,"text":21,"correct":18},"C","气压",{"key":23,"text":24,"correct":18},"D","严密性","本题考查的是通风与空调系统的检测与试验。开式水箱（罐）在连接管道前，应进行满水试验，换热器及密闭容器在连接管道前，应进行水压试验。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]