[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112009":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1112009,787,1,"单选题","空调水管道系统绝热施工应在（ ）进行。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","空调水管路系统试压和防腐处理结束后",true,{"key":16,"text":17,"correct":18},"B","空调风管系统设备绝热之前",false,{"key":20,"text":21,"correct":18},"C","空调风管系统风管绝热之后",{"key":23,"text":24,"correct":18},"D","空调水管路系统试压之前","本题考查的是通风与空调防腐绝热的技术要求。空调水系统和制冷系统管道的绝热施工，应在管路系统强度与严密性检验合格和防腐处理结束后进行。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]