[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112008":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1112008,787,1,"单选题","通风与空调工程的施工单位通过系统（ ）后，即可进入竣工验收。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","测试合格",false,{"key":16,"text":17,"correct":14},"B","设备单机试运转及调整",{"key":19,"text":20,"correct":21},"C","无生产负荷联合试运转与调试",true,{"key":23,"text":24,"correct":14},"D","综合效能测定及调整","本题考查的是风管系统制作安装的施工技术要求。施工单位通过系统无生产负荷联合试运转与调试后，即可进入竣工验收。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]