[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112004":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1112004,787,1,"单选题","建筑室内配管配线中，管内穿导线的紧后工序是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","导线绑扎",false,{"key":16,"text":17,"correct":14},"B","放线断线",{"key":19,"text":20,"correct":21},"C","导线并头绝缘",true,{"key":23,"text":24,"correct":14},"D","线路检查","本题考查的是建筑电气工程施工程序。管内穿线施工程序：选择导线→管内穿引线→导线与引线的绑扎→放护圈（金属导管敷设时）→穿导线→导线并头绝缘→线路检查→绝缘测试。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]