[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112003":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1112003,787,1,"单选题","在动力设备的施工程序中，“设备安装”的紧后工作是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","控制设备安装",false,{"key":16,"text":17,"correct":14},"B","电机干燥",{"key":19,"text":20,"correct":21},"C","电动机检查.接线",true,{"key":23,"text":24,"correct":14},"D","送电前的检查","本题考查的是建筑电气工程施工程序。动力设备施工程序：设备开箱检查→设备安装→电动机检查、接线→ 电动机干燥（受潮时）→控制设备安装→送电前的检查→送电运行。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]