[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111998":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1111998,787,1,"单选题","母线槽施工中在母线槽安装完毕之后，应进行（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","交接试验",false,{"key":16,"text":17,"correct":18},"B","通电前绝缘测试",true,{"key":20,"text":21,"correct":14},"C","送电前检查",{"key":23,"text":24,"correct":14},"D","送电验收","本题考查的是建筑电气工程施工程序。母线槽施工程序：开箱检查→支架安装→单节母线槽绝缘测试→母线槽安装→通电前绝缘测试→送电验收。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]