[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111997":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1111997,787,1,"单选题","开关柜、配电柜的施工程序为：开箱检查→二次搬运→基础框架制作安装→（ ）→试验调整→送电运行验收。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","柜体固定→二次线路连接→母线连接",false,{"key":16,"text":17,"correct":18},"B","柜体固定→母线连接→二次线路连接",true,{"key":20,"text":21,"correct":14},"C","二次线路连接→母线连接→柜体固定",{"key":23,"text":24,"correct":14},"D","母线连接→二次线路连接→柜体固定","本题考查的是建筑电气工程施工程序。开关柜、配电柜的安装顺序：开箱检查→二次搬运→基础框架制作安装→柜体固定→母线连接→二次线路连接→试验调整→送电运行验收。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]