[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111991":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1111991,787,1,"单选题","下列关于耐火喷涂料施工技术要求的说法，错误的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","喷涂方向与受喷面成60°~75°夹角",true,{"key":16,"text":17,"correct":18},"B","喷涂应分段连续进行",false,{"key":20,"text":21,"correct":18},"C","喷涂料应采用半干法喷涂",{"key":23,"text":24,"correct":18},"D","施工中断时，宜将接槎处做成直槎","喷涂方向应垂直于受喷面，喷嘴与喷涂面的距离宜为1～1.5m，喷嘴应不断地进行螺旋式移动，使粗细颗粒分布均匀；",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]