[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111990":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1111990,787,1,"单选题","根据《工业炉窑砌筑工程施工及验收范》，不属于工序交接证明书内容的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","隐蔽工程验收合格的证明",false,{"key":16,"text":17,"correct":14},"B","焊接严密性试验合格的证明",{"key":19,"text":20,"correct":21},"C","耐火材料的验收合格证明",true,{"key":23,"text":24,"correct":14},"D","上道工序成果的保护要求","工序交接证明书应包括的内容 1.炉子中心线和控制标高的测量记录及必要的沉降观测点的测量记录； 2.隐蔽工程的验收合格证明； 3.炉体冷却装置、管道和炉壳的试压记录及焊接严密性试验合格证明； 4.钢结构和炉内轨道等安装位置的主要尺寸复测记录； 5.动态炉窑或炉子的可动部分试运转合格证明； 6.炉内托砖板和锚固件等的位置、尺寸及焊接质量的检查合格证明； 7.上道工序成果的保护要求。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]